Financial Services Headquarters
Owner-side controls for a headquarters fit-out with a lease expiry that would not move.
- Owner
- Confidential
- Location
- U.S.
- Market
- Commercial
- Our role
- Owner’s representation
- Scale
- 6 floors
- Completed
- 2023
Owner-side controls and reporting for a trading floor and headquarters fit-out with a fixed lease expiry behind it.
The tenant’s old lease expired on a fixed date, with holdover rent that would have cost far more than any acceleration. Six floors of offices and a trading floor needed power, cooling and technology that had to be installed and tested before a single trader could move. The owner needed someone on its side of the table who could read the contractor’s schedule and costs critically.
The approach.

- 01
The owner’s eyes on the schedule
We reviewed every contractor update against the baseline and flagged float erosion on the technology path within days.
- 02
Long-lead items tracked weekly
Switchgear, cooling units and trading floor equipment were tracked from submittal to delivery against need-by dates.
- 03
Cost forecast against the lease
We priced acceleration options against holdover cost so the owner could make each decision on numbers, not instinct.
- 04
Move-in readiness
A move-in readiness tracker tied construction, IT and furniture to each floor’s move date.
The outcome.
“A lease date is a hard stop with a price tag. We showed the owner that price every week so the choices were easy.”
Owner’s representative, KonradBeck