Highways & Roads · 2024

Managed Lanes Corridor

Five contracts, one corridor and one integrated schedule, delivered under live traffic.

Owner
Confidential
Location
U.S.
Market
Highways & Roads
Our role
Planning & scheduling
Scale
18 corridor miles
Completed
2024
The brief

Multi-contract schedule integration for a tolled managed-lanes corridor built under live traffic.

The agency split 18 miles of managed lanes into five separate construction contracts, with utility relocations and tolling systems integration depending on all of them. Each contractor scheduled its own work. The handoffs between them were not tied together anywhere, and the agency could not see the true opening date.

How we controlled it

The approach.

  1. 01

    Interface milestones defined

    We mapped every handoff between contracts, utilities and tolling as a shared interface milestone with an owner and a date.

  2. 02

    One integrated schedule

    All five contract schedules were linked in Primavera P6 through those milestones, giving the agency one corridor-wide critical path.

  3. 03

    Traffic stages in the logic

    Lane closure windows and traffic switches were modeled as constraints, so resequencing proposals were tested before approval.

  4. 04

    Time impact analysis on delays

    Each delay event got a time impact analysis, so the agency knew whether it touched the opening date before negotiating.

The outcome.

5Contracts on one critical path
62Interface milestones tracked
31Days saved through resequencing
18Time impact analyses completed

“Five good schedules can still add up to one late corridor. The risk lives in the handoffs, so that is where we looked.”

Lead planner, KonradBeck