Sports & Entertainment · 2025

Live-Events Arena

An embedded controls team kept schedule, cost and risk in one view until a sold-out opening night.

Owner
Confidential
Location
U.S.
Market
Sports & Entertainment
Our role
Integrated project controls
Scale
$620M arena
Completed
2025
The brief

A full controls team embedded on an arena build that had an opening-night date sold out before the steel topped out.

Opening night was announced and sold out before the steel topped out. The arena had more than 40 contract packages, a long-span roof on the critical path and a technology fit-out that could not start until the building was dry. The owner was reading weekly reports from different parties that did not agree with each other.

How we controlled it

The approach.

  1. 01

    Embedded controls team

    Schedulers, cost engineers and a risk lead sat with the owner’s team on site, owning one integrated project controls system.

  2. 02

    Opening night as the anchor

    The Primavera P6 schedule was built back from opening night, with float to that date tracked for every package.

  3. 03

    Earned value on every package

    CPI and SPI by package showed where performance was slipping weeks before it showed up in the milestones.

  4. 04

    Weekly risk burn-down

    A live risk register with owners and dates drove weekly decisions on acceleration, resequencing and contingency.

The outcome.

41Contract packages integrated
23Days recovered on the critical path
0.98Final cost performance index
On dateOpening night

“When the date is printed on a ticket, you cannot wait for the monthly report. We gave the owner the truth every week.”

Project controls director, KonradBeck
Sports & Entertainment