Project controls since 2021 Scheduling · Cost · Risk · Advisory · Newark, NJ CareersNewsroomJoin our benchProject map
Resolve · Claims & Delay Analysis

Prove the delay. Price the impact.

Time impact analysis, windows analysis and cost quantification that establish who caused what, how many days it cost and what it is worth, in a form that stands up to review.

Why it matters.

01

Entitlement is decided by evidence

A delay that everyone remembers is worth nothing without contemporaneous records and a credible analysis. Memory loses to documentation.

02

Small claims grow when ignored

An unanswered time extension request turns into a disputed claim, then a formal dispute, at a cost far beyond the original issue.

03

Methods matter

The wrong analysis method, or the right one done poorly, can sink a strong position. Reviewers look at the method before they look at the result.

Our approach

How we work.

  1. 01

    Contemporaneous delay tracking

    Delay events logged and analyzed as they happen, with notices and records captured while the facts are fresh.

  2. 02

    Time impact analysis

    Fragnets inserted into the schedule current at the time of the event, showing the effect on the critical path and the completion date.

  3. 03

    Windows and as-planned versus as-built analysis

    Retrospective methods chosen to fit the records available and the contract, following AACE forensic schedule analysis practice.

  4. 04

    Concurrency and responsibility

    Overlapping delays separated by cause and party, so excusable, compensable and contractor-caused time are each accounted for.

  5. 05

    Cost quantification

    Extended general conditions, escalation, disruption and acceleration costs priced and tied back to the delay periods that caused them.

What you receive.

Every engagement is scoped to the project. These are the core outputs clients can expect.

Delay event logContemporaneous

Each event with its dates, notices, records and status.

Time impact analysesProspective

Schedule fragnets and the resulting change to the completion date.

Retrospective delay reportForensic

Windows or as-built analysis with findings by period and by party.

Quantum assessmentCost

Priced delay and disruption costs with the backup behind each figure.

Negotiation support packResolution

Summary findings, exhibits and positions ready for settlement discussions.

In practice · On-Site Power Plant

A multi-party claim, settled without arbitration.

On the on-site power plant, several parties had competing time extension requests. We built a contemporaneous delay analysis period by period, separated concurrent delays by cause and gave every party the same evidence to negotiate from. The request was resolved without going to arbitration.

120 MW
Plant capacity
0
Arbitration hearings needed
2026
Engagement year

Questions clients ask us.

Do you work for owners or contractors?

Both. Our analysis follows the evidence. A credible method is what gives either side a position worth defending.

Which delay analysis method do you use?

The one that fits the contract, the records and the question being asked. We follow AACE forensic schedule analysis practice and explain why the chosen method fits.

Can you help before a claim exists?

Yes, and that is where it pays most. Contemporaneous time impact analysis resolves most delays while the project is still moving.

Claims & Delay Analysis

Turn complexity into clarity.

Tell us what is keeping the project up at night. We will tell you where the schedule, cost and risk really stand.